2018 Paving and Overlay Schedule

Precinct 3 has completed the following 2.43 miles of gravel roads which are now paved as of the 2018 paving season.

​EASY ROAD         .93 mile
​CEMETARY RD.   .82 mile
​​SNIDER RD.         .69 mile    
​All roads have new flex base materials, new tin horns, and drainage infrastructure, ditch work.

​In addition we overlayed - (chipseal coated) 4.07 miles
​N CZECH HALL    2.03 mile    2nd coat
​GROPPE               1.04 mile      "
​EASY                     1.00 mile      "

​Chipseal - 31.98 combined miles
​OLD RAILROAD  
​OLD TOKIO
​TOKIO LOOP
​CHUDEJ SPUR
​CHUDEJ LANE
​BUGTUSSEL
​WINDSONG
​WINDCHIME
​GREENMEADOW
​WILLIE NELSON
​MARABLE
​HAJEK
​ROGERS HILL
​PLEASANT GROVE
​WAGONER
​MARY WARE
​BERGER
​MELLGREN
​UPTMORE
​BRICKYARD
​SNIDER
​E HILL TOP
​OLD DALLAS
​OLD LEROY
​WATER STREET
​ELENOR
​BISHOP
​BUNCHE
​MORAN
​LEO
​BAESE